    Were there mistakes during the build process like lowballing spending figures or building time so they are permitted to build or did they just royally fuck up some other way?

    • @[email protected]
      link
      fedilink
      English
      31 year ago

      It just seems to be a general issue in the industry and not specific to this plant or the US.

      Flamanville-3 in France is 5 years overrun already and is projected to be operational 12 years from now. It’s budget ballooned from 3.3B to 20B euros.

      Olkiluoto-3 was only delayed a year, but the budget went from 3 to 11B Euro.

      Hinkley Point C project is behind and esyimates have gone from £16B to almost £30B.