The project’s cost has risen to 11.8 billion euros, and its completion dates have been repeatedly postponed.
Negotiations for additional funding have not resulted in an agreement, leading to litigation.
The court ruled that the price fluctuation clause does not obligate partners to provide additional funding.
You must log in or register to comment.
Well, there is a contract stating who pays what, and it explicitely states that the government part of that is fixed. Pacta sunt servanda. The court basically declared what was already in the contract.