• @[email protected]
    link
    fedilink
    43
    edit-2
    16 hours ago

    On-prem still has its uses
    Platter harddrives are still useful
    Tapes and tapedrives aren’t obsolete

    • @gmtom
      link
      49 hours ago

      If you’re not archiving old data on tapes and shipping them off to a converted bomb shelter, you’re not doing it right.

      • @[email protected]
        link
        fedilink
        48 hours ago

        That is literally what we do at my job.
        Three copies: One for the client who paid for it, one for us (internal processing and testing only), and one as a backup goes to a storage location that is a converted cold war era bomb shelter.

    • Scrubbles
      link
      fedilink
      English
      3815 hours ago

      Oh god my story. Okay so I was building out a video transcoding service for a company. We all know video transcoding is hella expensive. So I’m using kubernetes to help manage scale, and we’re on the cloud. I warn them hey, cloud is hella expensive, this is going to be… a lot. Well what do you recommend? Glad you asked, and I pitched that we have 3 heavy server nodes sitting either in a rack if we want it official, or even we were small enough we could just have them in the office. They would be VPN’d into the cluster, members of the cluster, and those get the priority. If a transcode job comes in use those nodes, only spin up cloud nodes if the scale is too high. I quoted about 20k for 3 beefy performant machines for the node.

      Executives balked at the price. Way too much money, what a ridiculous idea anyway, we’re a cloud company.

      Two months into the cloud only solution they were averaging 12 grand just on CPU compute! Why is it so high?! That’s ridiculous!

      Absolute fuckers, the morons. I swear I’ve seen so many companies hemorrhage money because they refuse to listen to legit experts in the field. You fuckers, I was trying to save you money, but no your MBA and accounting degrees taught you how to run fucking cloud operations.

      • Badabinski
        link
        fedilink
        1314 hours ago

        I hate that it’s so hard to get these people to agree to capex. My current company runs a few datacenters, and we have some teams that use them for their base load. It saves a shitload of money! Like, I don’t get why this is a concept that MBAs reject. You don’t have to go all in on capex for your infrastructure, just find a nice mix of capex/opex. If you’re afraid that you won’t use the shit you bought later on, then you should probably make sure that the market is there for whatever you’re selling before you dive in headfirst.

      • @[email protected]
        link
        fedilink
        9
        edit-2
        15 hours ago

        We spent several hundreds of thousands of dollars last year doing geophysical processing in azure. But it was an emergency: It was a hot fix to avoid losing out on hundred times that amount. Turned out the contract negotiator never bothered telling operations that they agreed to deliver the data with some processing already applied.

        We considered building a processing cluster on site, but buying the necessary hardware and shipping it halfway around the world in a timely manner would’ve been even more costly. Plus I would be the one who had to build the rig, and I was all tied up on a different project a few countries over at that time.

    • slazer2au
      link
      English
      311 hours ago

      Also, do you really need high performance SSDs? Are you actually writing the drive volume a day?