Scene: Surprise meeting with the project owner 0-3 days before the go-live date

“Hey team, the business and I have decided to postpone the project release by n=1-3 months because [they aren’t ready for it / it isn’t finished /regulatory reasons]. And since we have some extra time now, we can tie up all the loose ends on this project (i.e., ‘we’ve added n+1 months worth of backlog items to the MVP’).”

I’m still a greenish dev, so maybe this is normal, but I’ve had the same story going on for over a year now, and it’s really starting to burn me out. In the beginning, I was optimistic. Now I just hope for the project to fail, or me to get off somehow, but this thing just won’t die.

Anyone with experience on similar projects able to share words of advice? Do they ever end up working out? Seems there’s a death spiral, since we are always rushing to a deadline, forgoing tests and quality but never cleaning up our mess because we’re already behind. Yet I somehow feel like I’m the crazy one for thinking this 6-month “quick” side project turned 2+ year half-rewrite will have trouble meeting it’s Nth deadline.

  • Royce
    link
    fedilink
    810 months ago

    @yournameplease These things are, unfortunately, pretty common.

    OP admitted they were pretty green though, so they’ll learn with time what makes a good employer for their work style.

    Honestly, I’d say stick with it for a bit just to have the experience. Then move on to a different company, which will be a different experience. If it’s better, they’ll appreciate their new job; if it’s worse, they’ll know that their first job wasn’t as bad as they thought.